Stages of project implementation
Scientific and engineering developments. Creation of technical regulations and production line concept:
- Research works on the development of technological processes and the creation of production regulations.
- Development of the design documentation for the experimental line.
- Modeling of production processes and technological nodes (with the construction of a VR model).
Done
Obtaining permit documentation and development of technological plans for the execution of works:
- Legal registration of the eco-industrial park.
- Obtaining permits for extracting raw materials.
- Developing project documentation for construction, and its examination.
- Conducting tender procedures and obtaining a construction permit.
- Preparatory work on the site, ordering equipment, and mining and quarry works.
Execution by the end of 2023
Construction and commissioning of production:
- Ordering equipment.
- Installation of engineering networks of buildings and production facilities.
- Installation and commissioning works.
- Commissioning and production certification.
- Start of sales of finished products.
Execution by the end of May 2025
Project implementation schedule
Calendar-network schedule of project implementation